Please be advised of upcoming PSEG milling and paving in Summit, weather permitting. Schedule subject to change.
The current PSEG schedule for milling and paving the following streets the week of September 15 is below.
Please note the Blackburn Road milling and paving is scheduled for after drop off and before pickup as well as after pickup to avoid disruption to Franklin Elementary School.
The schedule is provided by PSEG and could change depending on weather or crew availability. The City of Summit shares this for your planning purposes.
Please park on neighboring streets during the milling or paving day scheduled for your street.
Milling
Monday, 9/15/2025 – 8am-5pm
Knob Hill Dr – Ramsey Dr to Twombley Dr
Twombley Dr Loop
Blackburn Rd – Division Ave to Twombley Dr (Start)
Tuesday, 9/16/2025 – 8am-1pm
Blackburn Rd – Twombley Dr to Valley View Ave (Finish)
Sunset Dr – Division Ave to Valley View Ave
Edgemont Ave – Summit Ave to Badeau Ave
Paving
Wednesday, 9/17/2025 – 8am-5pm
Knob Hill Dr – Ramsey Dr to Twombley Dr
Twombley Dr Loop
Blackburn Rd – Division Ave to Valley View Ave (Start)
Thursday, 9/18/2025 – 8am-5pm
Blackburn Rd – Division Ave to Valley View Ave (Finish)
Sunset Dr – Division Ave to Valley View Ave
Edgemont Ave– Summit Ave to Badeau Ave
Please note limits are estimated and will be adjusted as needed in the field.
Roads will be closed during project work and for an hour or so after paving is complete to allow the pavement to cure. Residents are asked to park vehicles on neighboring side streets before 7AM, and during the day/overnight, as needed. Police will be notified of overnight and extended parking on side streets.