Going forward, please use this link to check the city website for the most current schedule; this information is frequently updated throughout the week as PSEG provides us with schedule updates.
Please see below for the updated schedule as of 10/20/25 provided by PSE&G for upcoming milling and paving on several Summit streets, weather permitting and subject to change.
Road closures and detours will be in effect during project work and police will be onsite to direct traffic. Residents should park on neighboring side streets while roads are closed during project work.
All work will be completed between the hours of 8AM and 5PM.
Milling:
Tuesday 10/21/25
Evergreen Rd from Colonial Rd to dead end
Ashland Rd between Linda Ln and Manor Hill Rd (start)
Wednesday 10/22/25
Ashland Rd between Linda Ln and Manor Hill Rd (continue)
Thursday 10/23/25
Ashland Rd between Linda Ln and Manor Hill Rd (finish)
Baltusrol Pl from Baltusrol Rd to north of Hughes Pl
Friday 10/24/25
Springfield Ave (start): from Passaic Ave to Oakley Ave
Monday 10/27/25
Springfield Ave (continue): from Oakley Ave to High St
Tuesday 10/28/25
Springfield Ave (finish): High St to New England Ave
Paving:
Tuesday 10/28/25
Springfield Ave (start): from Passaic Ave to Pine Grove Ave
Wednesday 10/29/25
Springfield Ave (finish): Pine Grove Ave to New England Ave
This information is available on the city website at cityofsummit.org/CivicAlerts.aspx?AID=2547.