Please be advised of the revised schedule for the Ox Bow Lane construction project, subject to change due to weather.

Monday, May 13: Final paving preparation
Tuesday, May 14: Paving
Wednesday, May 15: Cleanup
Thursday, May 16: Striping

Updates will be shared on social media and at cityofsummit.org/construction.