Please be advised of the following schedule for construction work on Colonial Road, weather permitting:
Monday, December 18: Drainage work
Tuesday, December 19: Milling of the roadway
Wednesday, December 20: Paving of the roadway
Work will be performed between the hours of 8AM and 5PM. Residents should park on neighboring side streets during milling and paving operations when the road is fully closed. Police will be on-site to direct traffic during project work.