Please be advised: On Wednesday, May 31, work will begin on Summit Avenue to upgrade ADA compliant ramps. Work will be performed between the hours of 8AM and 5PM and is expected to take five to six days to complete, weather permitting. Police will be onsite to direct traffic and emergency vehicles will always have access. Milling operations on Summit Avenue are expected to begin in mid-June, which will be followed by paving operations. Milling and paving dates will be shared and posted to the city website once they are confirmed.