The contractor for the New Jersey American Water project to install new water mains on Morris Avenue is providing a progress update.

The expected completion date has been pushed to November 18 due to inclement weather throughout the month of October. All water main installations will be completed by tonight, November 1, with remaining work to be completed on side streets. Work hours are Monday through Friday from 8PM to 5AM.

Please contact New Jersey American Water at 1-800-272-1325 with any questions.