CONSTRUCTION UPDATES

FERNWOOD, RIDGE, DRUID HILL, FAIRVIEW

Limits: Entire lengths of all streets. 
Scope: Drainage upgrades, installation of granite block curbing, ADA upgrades, and full milling and roadway resurfacing.
Contractor: Reivax Contracting
Start Date:  Tuesday May 19, 2015.
End Date: Friday, August 31, 2015.
Update:  Drainage work has progressed to Druid Hill.  Access to driveways may be restricted when pipe is being installed. of the ongoing construction and avoid all fenced off areas when approaching the station and disposal area.    

TIER PARKING GARAGE - 466 Springfield Avenue

Limits: Tier Garage - Entrance from Springfield Avenue
Scope: A private developer is reconstructing 466 Springfield Avenue. Due to the nature of the work, cars will only be able to exit the Tier Garage onto Springfield Avenue. The Tier Garage will be accessible from Maple Street. The detour will be suspended during November & December of 2014.
Start Date: October 2013.
End Date: July 2015.

Click HERE for the detour plan.

 

MORRIS AVENUE BRIDGE REPLACEMENT

Limits: Morris Avenue Bridge over NJ Transit tracks between Springfield Avenue and Kent Place Boulevard.
Scope: Full replacement of bridge structure.  This project is being completed by New Jersey Transit and will require a full closure of the bridge for approximately eighteen (18) months.  NJ Transit is hosting a formal meeting at City Hall at 4pm on Wednesday, July 15, 2015.   The DETOUR MAP can be found here. 
Start Date: On or about July 29, 2015
End Date: January 25, 2017

ROUTE 78 Resurfacing (State Project)

Limits: Mile Posts 42.2 to 50.6
Scope: Overlay of existing pavements and ADA upgrades. 
Start Date:  Mid-June 2015
End Date: September 2015
Update:  This is a State project that will be completed off peak hours.  

COUNTY PROJECTS

The following County projects are currently underway:

MORRIS AVENUE & SPRINGFIELD AVENUE PAVING

Limits: Morris Avenue (Springfield Avenue south to Huntley Taverne)
             Springfield Avenue (Huntley Taverne to Route 24)
Scope: Resurfacing and ADA upgrades.  Paving work will be at night.
Milling Dates:  July 20 - July 23 weather permitting
Paving Dates: July 22 - July 27 weather permitting
Link to County Site: Click HERE 

THREE (3) TRAFFIC SIGNAL REPLACEMENTS

  1. PASSAIC AVENUE & KENT PLACE BOULEVARD
  2. SPRINGFIELD AVENUE & PASSAIC AVENUE
  3. SPRINGFIELD AVENUE & NEW ENGLAND DRIVE

Scope: Replacement of Existing Traffic Signals.  
Start Date:  June 3, 2015
End Date: September 3, 2015
Link to County Site: Click HERE 

COMPLETED PROJECTS

These projects are completed. Should you have any concerns please contact the Engineering Division at 908.273.6404.

Essex Road

Magnolia, Montview, Primrose, Surrey

DeForest Avenue

Badeau, Llewlleyn, Shadyside

Passaic Avenue Paving

Ashland Road Paving

Transfer Station Slab Replacement